Mission Status Center

STS-122 Quick-Look

Meet the Crew

Launch Windows

Countdown Timeline

Launch Timeline

Master Flight Plan

Key Mission Personnel

Shuttle Flight History

STS-122 Archive




Spaceflight Now +



Subscribe to Spaceflight Now Plus for access to our extensive video collections!
How do I sign up?
Video archive

Harmony's big move

The station's new Harmony module is detached from the Unity hub and moved to its permanent location on the Destiny lab.

 Play

Delta 4-Heavy launch

The first operational Delta 4-Heavy rocket launches the final Defense Support Program missile warning satellite for the Air Force.

 Full coverage

Columbus readied

The European Space Agency's Columbus laboratory module moves to pad 39A and placed aboard shuttle Atlantis for launch.

 To pad | Installed

Station port moved

The station crew uses the robot arm to detach the main shuttle docking port and mount it to the new Harmony module Nov. 12.

 Play

Atlantis rolls out

Space shuttle Atlantis rolls from the Vehicle Assembly Building to pad 39A for its December launch with the Columbus module.

 Play

Atlantis goes vertical

Atlantis is hoisted upright and maneuvered into position for attachment to the external tank and boosters.

 Play

Space station EVA

This Expedition 16 status briefing recaps the Nov. 9 spacewalk that prepared the station's shuttle docking port for relocation to the new Harmony module.

 Play

STS-120 landing

Discovery returns home to the Florida spaceport after its two-week mission.

 Full coverage

Become a subscriber
More video



ECO sensor No. 3 fails initial health check
BY WILLIAM HARWOOD
STORY WRITTEN FOR CBS NEWS "SPACE PLACE" & USED WITH PERMISSION
Posted: December 9, 2007

Presumably dashing hopes of finally launching shuttle Atlantis on a critical space station assembly mission today, one of the four low-level engine cutoff - ECO - sensors in the hydrogen section of the shuttle Atlantis' external tank failed to perform properly during initial tests after being submerged in supercold propellant. NASA managers said Saturday they would proceed with launch today only if all four sensors and associated instrumentation worked flawlessly.

Fueling began at 5:56 a.m. and by 6:48 a.m., the loading process transitioned to "fast fill." A few minutes later, NASA commentator George Diller reported what engineers initially believed was good news.

"The liquid hydrogen sensors have been cycled and they are all confirmed to be working properly," he said. "Once again, at this time, all four liquid hydrogen sensors are working. This was somewhat predicted based on past tanking attempts when we had a problem with the sensors and then tanked a second time and the sensors have worked properly. So right now, this is consistent with our experience base. And all four hydrogen sensors are currently operating."

But moments later, sensor No. 3 apparently failed to respond properly.

"One of the liquid hydrogen sensorsw, No. 3, has failed," Diller said. "Standing by for further action. ... This is not good news."

Engineers continued filling Atlantis' external tank to collect additional data but Diller did not immediately say whether launch had been scrubbed for the day. NASA has a flight rule that permits a launch if three of four sensors are working properly, but NASA managers said Saturday any problem with the sensors today would result in a scrub.

"So far, an initial scrub has not been declared," Diller said.

Three of the four sensors, including No. 3, did not respond properly during fueling Thursday, derailing the first attempt to launch Atlantis. Because the system is suspect - and because repairs are not possible before the end of the current launch window Dec. 13 - NASA's Mission Management Team required all four sensors and associated instrumentation to be working properly today for the countdown to proceed.

The goal of Atlantis' mission is to deliver the European Space Agency's Columbus research lab to the international space station along with French astronaut Leopold Eyharts, who will replace Expedition 16 flight engineer Dan Tani.

Three spacewalks are planned to prepare Columbus for installation; to install two experiments on its hull; and to replace a spent nitrogen tank used to pressurize the station's ammonia cooling system. The nitrogen tank and a failed gyroscope will be moved back to the shuttle for return to Earth.

But NASA only had until Dec. 13 to get Atlantis off the ground because of temperature and power issues related to the angle between the sun and the plane of the space station's orbit. The window reopens Dec. 30, but any delay past Dec. 13 would push the flight into January to avoid countdown software issues due to the end-of-year rollover.

Engineers cannot access all of the ECO sensor circuitry at the launch pad, raising the possibility of a rollback to the Vehicle Assembly Building to remove the orbiter from the external tank for more extensive troubleshooting. But no such decisions have been made as of this writing.

The ECO sensors are part of a backup system intended to detect low fuel levels in time to prevent the shuttle's main engines from draining the tank after some other problem that might cause the powerplants to use up hydrogen faster than expected. Running out of fuel during engine operation likely would trigger a catastrophic failure.

In the wake of earlier problems with the cutoff sensors, NASA implemented a flight rule change that would permit a countdown to proceed if three of four sensors were operating normally and certain other conditions were met.

But engineers do not yet know what caused two sensors to "fail wet" during fueling Thursday or why a third sensor did the same during de-tanking operations. Because the system is suspect, the flight crew office proposed proceeding with launch Sunday if, and only if, all four sensors are operating normally.

STS-134 Patch

Free shipping to U.S. addresses!

The final planned flight of space shuttle Endeavour is symbolized in the official embroidered crew patch for STS-134. Available in our store!
 U.S. STORE
 WORLDWIDE STORE

Final Shuttle Mission Patch

Free shipping to U.S. addresses!

The crew emblem for the final space shuttle mission is now available in our store. Get this piece of history!
 U.S. STORE
 WORLDWIDE STORE

Apollo Collage
This beautiful one piece set features the Apollo program emblem surrounded by the individual mission logos.
 U.S. STORE

STS-133 Patch

Free shipping to U.S. addresses!

The final planned flight of space shuttle Discovery is symbolized in the official embroidered crew patch for STS-133. Available in our store!
 U.S. STORE
 WORLDWIDE STORE

Anniversary Shuttle Patch

Free shipping to U.S. addresses!

This embroidered patch commemorates the 30th anniversary of the Space Shuttle Program. The design features the space shuttle Columbia's historic maiden flight of April 12, 1981.
 U.S. STORE
 WORLDWIDE STORE

Mercury anniversary

Free shipping to U.S. addresses!


Celebrate the 50th anniversary of Alan Shephard's historic Mercury mission with this collectors' item, the official commemorative embroidered patch.
 U.S. STORE
 WORLDWIDE STORE

Fallen Heroes Patch Collection
The official patches from Apollo 1, the shuttle Challenger and Columbia crews are available in the store.