GAO: Medium-class missions face cost, schedule concerns
BY STEPHEN CLARK
SPACEFLIGHT NOW

Posted: November 23, 2010


Bookmark and Share

The next generation of NASA remote sensing satellites and space science probes could be burdened by rising launch costs and delays as the agency incorporates new medium-lift rockets, according to a Government Accountability Office report released Monday.


File photo of a Delta 2 rocket launch. Credit: Bill Hartenstein/United Launch Alliance
 
The uncertainty surrounds 12 to 14 science missions through 2020 that have not yet received launch vehicle assignments, the government watchdog report said.

NASA is ending its use of the Delta 2 rocket, a workhorse launcher that has delivered nearly 60 percent of the agency's scientific satellites to space since 1998.

NASA is shifting future medium-class missions to SpaceX's Falcon 9 rocket and the Taurus 2 launcher being developed by Orbital Sciences Corp. The GAO found both vehicles serve the same market as the Delta 2 and have similar costs.

But the Falcon 9 and Taurus 2 are not certified to launch NASA's most expensive and important science missions.

United Launch Alliance has three more NASA missions on its Delta 2 manifest. Parts for producing five more Delta 2 rockets are also available, but there are high costs of modifying and maintaining launch pads to host any extra flights, according to the GAO.

The report addressed NASA's efforts to support the remaining Delta 2 flights and the agency's medium-class launch strategy.

"NASA is taking an appropriate approach to help ensure the success of the remaining Delta 2 missions by adequately addressing workforce, support, and launch infrastructure risks," the report said. "Nevertheless, an affordable and reliable medium launch capability is critical to NASA meeting its scientific goals."

Most of the medium-class missions in NASA's portfolio are Earth observation satellites, which require polar orbit launches from West Coast sites at Vandenberg Air Force Base, Calif., or Kodiak Launch Complex in Alaska.

Neither company has an operational West Coast launch site. SpaceX plans to construct a Falcon 9 launch pad at Vandenberg, and Orbital is still evaluating potential sites for polar Taurus 2 missions.

The first NASA decision point is expected in the next few months. NASA must decide on a launch vehicle for three Earth observation satellites in 2011. The missions are due for liftoff in 2014 and 2015.

NASA is expected to settle on a rocket for the Soil Moisture Active and Passive, or SMAP, satellite by March. Other civil space missions scheduled for launch by 2015 and still lacking a launch vehicle assignment include the ice-mapping ICESat 2 spacecraft and the first member of NOAA's revamped polar-orbiting weather satellite fleet.

The Falcon 9 and Taurus 2 are already under NASA contracts to supply cargo to the International Space Station beginning in 2011 or 2012. The Launch Services Program, which manages launch contracts for NASA's robotic missions, has not yet awarded a flight to either rocket.


The first Falcon 9 rocket blasted off from Florida in June. Credit: Chris Thompson/SpaceX
 
The Falcon 9 is part of a NASA Launch Services contract announced in September that sets the pool of rockets available for the agency's unmanned missions. Orbital plans to add the Taurus 2 to NASA's mix of launch vehicles in 2011.

Competitions to launch individual spacecraft result in a task order that NASA issues to a specific booster. The certification process for the Falcon 9 rocket will begin when it receives its first task order, and the GAO predicts the Falcon 9 could be deemed ready to launch NASA's high-priority payloads by late 2013, assuming a contract award in early 2011.

The Taurus 2 is not eligible for a task order until it becomes part of the NASA Launch Services contract, which is not expected until at least late 2011.

The GAO report said NASA officials estimate it will cost about $25 million and take about three years to certify each new rocket, assuming there are no significant design changes or additional testing required.

"NASA has a plan in place for obtaining this capability through Orbital and SpaceX's vehicles, but past experience with other development programs and recent history with both vehicles indicate that maturing and certifying these vehicles for use by science missions is likely to prove more difficult and costly than currently anticipated," the report said.

The certification costs will be passed on to NASA's science mission directorate and could be assigned to the first mission to use a new rocket or spread over several projects, according to the GAO.

The watchdog agency also warned of potential launch delays stemming from setbacks in rocket development or the certification process.

"While NASA expects these vehicles will eventually become a viable option for medium class science missions, it is uncertain how long the process might take," the report said.