Flight 181: Ariane 5/ATV Countdown Timeline
SPACEFLIGHT NOW Posted: March 5, 2008
NOTE: GMT is +5 hours ahead of Eastern Standard Time.
| H-1 Day |
March 8, 2008 |
H-11:30:00 (1633:04 GMT)....Begin final countdown
H-07:30:00 (2033:04 GMT)....Test launcher electrical systems
H-07:30:00 (2033:04 GMT)....Configure first stage for fueling
H-06:00:00 (2203:04 GMT)....Prepare launch pad for final countdown
H-06:00:00 (2203:04 GMT)....Load flight software
H-06:00:00 (2203:04 GMT)....Test radio frequency links
H-06:00:00 (2203:04 GMT)....Align inertial guidance units
H-05:00:00 (2303:04 GMT)....Clear launch pad personnel
H-05:00:00 (2303:04 GMT)....Pressurize ground liquid hydrogen and liquid
oxygen tanks
H-05:00:00 (2303:04 GMT)....Pressurize first and second stage attitude
control systems
H-04:30:00 (2333:04 GMT)....Begin chilldown of ground propellant lines
|
|
| H-0 Day |
March 9, 2008 |
H-04:00:00 (0003:04 GMT)....Load first stage liquid hydrogen and liquid
oxygen
H-03:00:00 (0103:04 GMT)....Begin chilldown of Vulcain 2 first stage main
engine
H-02:00:00 (0203:04 GMT)....Transition to propellant topping mode
H-02:00:00 (0203:04 GMT)....Load final ATV software
H-00:30:00 (0333:04 GMT)....Prepare synchronized launch sequence
H-00:08:00 (0355:04 GMT)....ATV in launch configuration and on
internal power
H-00:07:00 (0356:04 GMT)....Begin synchronized launch sequence
H-00:06:30 (0356:34 GMT)....Terminate propellant topping
H-00:06:30 (0356:34 GMT)....Arm launcher ordnance
H-00:04:00 (0359:04 GMT)....Pressurize first stage liquid hydrogen and
liquid oxygen tanks
H-00:03:30 (0359:34 GMT)....Calculate official launch time
H-00:02:00 (0401:04 GMT)....Open Vulcain 2 bleeder valves and close
chilldown valves
H-00:00:50 (0402:14 GMT)....Switch launcher to on-board power
H-00:00:37 (0402:27 GMT)....Begin automatic ignition sequence and start
on-board recorders
H-00:00:22 (0402:42 GMT)....Activate first stage attitude control system
H-00:00:22 (0402:42 GMT)....Switch launcher to on-board control
H-00:00:06 (0402:58 GMT)....Start hydrogen burn-off igniters and retract
cryogenic umbilical arms
H-00:00:03 (0403:01 GMT)....Switch inertial guidance units to flight mode
H-00:00:02 (0403:02 GMT)....Open launch table water valves
H0 (0403:04 GMT)............Vulcain 2 engine ignition
|

Data Source: EADS Astrium
|
|
|
|
Apollo Collage
This beautiful one piece set features the Apollo program emblem surrounded by the individual mission logos.
U.S. STORE

STS-127 Patch
The official embroidered patch for shuttle Endeavour's flight to finish building Japanese section of the space station.
U.S. STORE
WORLDWIDE STORE



Hubble Patch
The official embroidered patch for mission STS-125, the space shuttle's last planned service call to the Hubble Space Telescope, is available for purchase.
U.S. STORE
WORLDWIDE STORE

Project Orion
The Orion crew exploration vehicle is NASA's first new human spacecraft developed since the space shuttle a quarter-century earlier. The capsule is one of the key elements of returning astronauts to the Moon.
U.S. STORE

Fallen Heroes Patch Collection
The official patches from Apollo 1, the shuttle Challenger and Columbia crews are available in the store.
U.S. STORE
WORLDWIDE STORE
|